Project 1 - Yellow pine Way, Hainault IG7

Project Summary

Year

2013 - complete

Address

Yellow pine Way, Hainault IG7

Project

Development of 24 units with 12000 sq. ft. with new basement for car parking for over 40 cars.

GDV

Over £5.7 million

Contract Value

£2.6 million

Demolished 96 garages to create the vacant land. Built a 12000 sq. ft. new basement with hand stitched reinforced concrete retaining walls, columns & a 400mm thick top slab. Conventional build from ground floor onwards.